Ilmi Solutions Oy will take part at Munchen Bauma 2019 from Monday to Thursday 8–11.4. You can find us from our partner CM Llamada stand: FN.623/9.

Be most welcome to take a moment with us on Down-the-hole hammering, CFA or Piling documentation system: Ilmi iPileCom system for Pile driving and Down-the-hole hammering.

Llamada P-105TT drilling RD-damwall

Llamada P-105TT can make SSAB RD-damwalls to very big dimensions, as in picture where it’s making 700mm x 18 m piles. It’s very strong machine while being light in weight as transport weight is only 46 t.
Documentation is easily done with integrated Ilmi iPileCom DTH monitoring system and transferred automatically to Ilmi iPileCom Cloud Office. .

Kuvat: Markus Valtanen & Mikko-Pekka Karlin, Kuulu Oy

Llamada and EGT-piling rigs had good start at Nordic working sites

First spanish Down the hole piling machine manufacturer Llamada P145EV has been delivered to Finland. It did one big dimension down the hole hammering job site “Tripla” in Finland before it continued to Åland. After that it done couple of sites in Sweden, Stockholm. Ilmi iPileCom DTH Down the hole piling documentation system got documentation in order and information to cloud service in all the sites.
EGT‘s rigs demand in Finland is good and we’ll deliver several new ones to Finland before summer.

Ilmi delivers robust multipurpose drilling rigs to Finland

Ilmi Solutions Oy has sold two robust E.G.T. Srl rigs to Destia Engineering
Oy
. Rigs are by an Italian machine manufacturer E.G.T. Srl. EGT MD series is standing for multipurposerigs, which are designed for drilling and anchoring work, small pile drilling with head hitting techiniques, as well as jet grouting. Both EGT MD815 and MD718 models are equipped at the factory so that they can doall of the above-mentioned drilling works. Ilmi Solutions Oy delivers these particular multi-purpose drilling rigs at the beginning of November 2016.

Destia http://destia.fi

Swedish piling contractor Hercules seeks benefits from Finnish pile driving documentation system

Swedish Hercules Grundläggning AB, and Finnish Ilmi Solutions Oy from Kuopio, Finland have signed a delivery contract about Ilmi iPileCom pile driving documentation system, Ilmi iPileCom.

– Such system will improve safety on job site. Assistant of the piling rig doesn’t have to be in the close perimeters of the hammer during driving process, says Jan-Erik Svensson from Hercules Grundläggning AB.

– Besides safety benefits, system will automatically instrument important process parameters in real time which will be presented for rig operator and are used for producing automated documentation, adds Tuukka Pasanen from Ilmi Solutions Oy.

Size and intelligent systems to Destia Down-the-Hole drilling

Destia Engineering Oy Finland carried out a largescale Down-The-Hole hammering job in Helsinki Eastern Pasila new center, Tripla . Destia Engineering Oy has successfully used the Spanish Llamada manufactured Down-The-Hole Hammering machine model P145EV , which is intended to be very demanding blind
bore. The machine delivered by Ilmi Solutions Oy, which also delivers Down-The-Hole hammering documentation system Ilmi iPileCom for DTH. Pile diameters used in Tripla
worksite are up to D1220 mm steel pipes. to support the safe piling created Report Ilmi iPileCom for DTH documentation system to ensure high-quality completion of the piling.

Year 2015 pile driving construction site winner has been documented with Ilmi iPileCom

Yearly elected 2015 pile driving work site winner 2015 has been selected by YIT Rakennus Oy / Infrapalvelut. Selected construction site was East Helsinki’s new shopping center i3. The choice was affected by the construction site arrangements, cooperation with all parties, work organization and well-functioning practices such as automated documentation system, Ilmi iPileCom use.

Ilmi`s automatic pile driving documentation eased considerably the site real-time monitoring and the preparation of the necessary protocols, says senior worksite manager Henri Kiiski.

Constructed mainly on the former seabed shopping center was challenging pile driving worksite. Under the building there are piles about 40 kilometers. With a big construction site tight schedule created its own pressure mainly in the manufacture carried out in two piles machine project protocols and follow-up work. Despite the challenges, piles at
best measured more than twice the capacity of the requirements were.